Date | Affected Points and Capacity Products | Level of Reduction | Type of Measure | Additional Remarks |
From 17 Apr 2023, 06:00 To 02 Feb 2024, 17:00 | Uberackern Entry Interruptible, DZK (interruptible) Uberackern 2 Entry Interruptible, DZK (interruptible)
USP Haidach Entry Interruptible, DZK/bFZK (interruptible)
| Increased probability of interruption | Maintenance Compressor Station Haiming | All firm entry products (bFZK, DZK, FZK) and all exit products (firm & interruptible) are not affected by this measure. |
From 08 May 2023, 07:00 To 12 May 2023, 18:00
| Uberackern Entry/Exit Interruptible, DZK (interruptible) Uberackern 2 Entry/Exit Interruptible, DZK (interruptible)
USP Haidach Entry/Exit Interruptible, DZK/bFZK (interruptible)
Haiming 2-RAGES/bn Entry/Exit Interruptible, DZK/bFZK/bFZK1 (interruptible)
Haiming 2-7F/bn Entry/Exit Interruptible, DZK/bFZK (interruptible)
| Increased probability of interruption | Maintenance Compressor Station Wertingen | |
From 20 June 2023, 07:00 To 21 June 2023, 17:00
| Uberackern Entry/Exit Interruptible, DZK (interruptible) Uberackern 2 Entry/Exit Interruptible, DZK (interruptible)
USP Haidach Entry/Exit Interruptible, DZK/bFZK (interruptible)
| Increased probability of interruption | Test Compressor Station Haiming | This measure can increase the interruption probability of interruptible and interruptible DZK/bFZK entry and exit capacities at Uberackern, Uberackern 2 and USP Haidach. |
From 17 July 2023, 07:00 To 20 July 2023, 18:00
| Uberackern Entry/Exit Interruptible, DZK (interruptible)
Uberackern 2 Entry/Exit Interruptible, DZK (interruptible)
USP Haidach Entry/Exit Interruptible, DZK/bFZK (interruptible)
Haiming 2-RAGES/bn Entry/Exit Interruptible, DZK/bFZK/bFZK1 (interruptible)
Haiming 2-7F/bn Entry/Exit Interruptible, DZK/bFZK (interruptible) | Increased probability of interruption | Maintenance Compressor Station Wertingen | |
From 17 July 2023, 07:00 To 21 July 2023, 17:00 | Inzenham-West USP Entry/Exit | Interruption of all entry and exit flows | Replacement of equipment | |
From 24 July 2023, 07:00 To 27 July 2023, 18:00
| Uberackern Entry/Exit Interruptible, DZK (interruptible)
Uberackern 2 Entry/Exit Interruptible, DZK (interruptible)
USP Haidach Entry/Exit Interruptible, DZK/bFZK (interruptible)
Haiming 2-RAGES/bn Entry/Exit Interruptible, DZK/bFZK/bFZK1 (interruptible)
Haiming 2-7F/bn Entry/Exit Interruptible, DZK/bFZK (interruptible) | Increased probability of interruption | Maintenance Compressor Station Wertingen | |
Cancelled From 18 Sept 2023, 06:00
To 29 Sept 2023, 06:00
| Uberackern Entry Interruptible, DZK (interruptible)
Uberackern 2 Entry Interruptible, DZK (interruptible)
USP Haidach Entry Interruptible, DZK/bFZK (interruptible)
| Increased probability of interruption | Maintenance Compressor Station Haiming
| All firm entry products (FZK, bFZK, DZK) and all exit products (firm and interruptible) are not affected by this measure.
|
From 09 October 2023, 07:00 To 15 October 2023, 18:00 | Uberackern Entry/Exit Interruptible, DZK (interruptible)
Uberackern 2 Entry/Exit Interruptible, DZK (interruptible)
USP Haidach Entry/Exit Interruptible, DZK/bFZK (interruptible)
Haiming 2-RAGES/bn Entry/Exit Interruptible, DZK/bFZK/bFZK1 (interruptible)
Haiming 2-7F/bn Entry/Exit Interruptible, DZK/bFZK (interruptible) | Increased probability of interruption | Maintenance Compressor Station Wertingen | |